Prysmian cable layer newbuilding project progresses

Prysmian Group is moving ahead with the construction of its fourth cable-layer. The keel was laid for its newbuild cable-laying vessel, Leonardo da Vinci, at the Vard shipyard in Norway in September 2019.

The DP3 cable-laying vessel is scheduled to be delivered from Vard in time for the vessel to enter service by Q2 2021.